Job Update

December 1
APPROVED & DEMOLITION
Construction
Plans have been fully approved and demolition starts November 15th construction starts December 1st.
November 1
Finally Plans
Approved

November 1st update from Architect Edgar Perez of “Pascual, Perez, Kiliddjian, Starr & Associates” that they are finalizing the plans and comments for submission for final review for the city of Fort Lauderdale. 

Once submitted plans shall be approved and ready for construction to start within 45 days or less  home team up construct gallery contact get

December 24
BUDGET & SCHEDULE
Go time

We finally got a final set of plans to submit to the city, we are submitting this week, and hopefully we'll have the 1st review by end of January, re submit all comments and hopefully final comments 1st week of February, so I would say by either end of February to beginning of March we should have a permit, this is according to what the city is being doing lately with time frames and we hope is right.

If this is all correct I should have the shell of the house done by August the latest, the house
should be about 90% completed by end of the
year. Im shooting for a 10 - 12 Month Construction Time Line.